Repairs to SpudCans of Sagar Ratna
Awarded by ONGC in 1997, with DOEIL working as subcontractor to Cochin
Shipyard Ltd., this Rs. 927 lacs job entailed repair of cracks and plating
renewal work on the spudcan of the rig. This was carried out under the
certification of American Bureau of Shipping and Noble Denton Associates.
For this job a heavy lift barge was required to be mobilized which could
act as a dry dock. Since no such dry dock of this size was available in
India, DOEIL solved this problem by thinking out of the box. It proposed
docking the rig on a semi-submersible, instead. A 22788 MT self propelled
semi submersible was mobilized, on which the rig was lifted out of the
water, allowing completion of work.